Diverse Civil were contracted by Sarah Constructions to carry out a bulk excavation for a mass concrete footing beneath the new d’Arenberg Cube multistorey building.

Our scope of works included:

  • Bulk excavation of rock for 1.5m deep concrete building pad. 
  • Base preparation for building pad and external concrete stairs.
  • Construction of a 5m wide rubble access road for future pavement. 
  • Retaining wall excavation, drainage installation and backfill.
  • Construction of temporary 6m wide rubble ring road around perimeter of building.
  • Stormwater pit and pipe installation.
  • Common service trenching.
  • Trenching and installation of pre-cast mechanical services pipework culvert.